Just west of the Pier Peddler, by the donor-inscribed stones, temporary fencing now cuts across the Grand Haven boardwalk. More fencing stands closer to the entrance to Grand Haven State Park. In Spring Lake Township, the North Bank Trail has been blocked between 148th Avenue and N. Fruitport Road since spring.
The two closures fall under different governments, a city and a township, but they come from the same kind of problem. In both places, something under the walking surface gave out. And the township's newest pavement is the reason the trail closure is only an inconvenience and not a dead end.
Sand Moving Under the Boardwalk Pavers
Repairs at Lighthouse Connector Park began Thursday, September 17, 2026. The City of Grand Haven expects the work to finish during the week of October 12. That means the fencing should come down in about a week, but treat the date as a target. As of early October, the city hadn't announced completion.
City officials told the Grand Haven Tribune that sand had been washing out from under the boardwalk's concrete pavers and leaving a void. As the concrete shifted and tipped, the decking took on extra weight and stress that could have led to more damage. Longtime Grand Haven resident and volunteer Ken Formsma alerted the city this spring. He has also led fundraising for the boardwalk over the years.
Crews are removing the existing concrete and pavers and building a base that can properly support the structure. Site Work Solutions of Zeeland is doing the work. City Council chose its not-to-exceed bid of $55,900 at the September 8 meeting, and the city is paying for it with leftover sidewalk repair money from this fiscal year. For a walk out to the pier heads, the practical point is that sections near the work site may close as the repairs move along, even where the fences don't block the boardwalk today.
Old Timbers Under the North Bank Trail
The North Bank Trail problem goes much deeper. On May 10, 2026, a section of the trail collapsed. Spring Lake Township says the cause is still unknown. Its best working theory is that the trail's land bridge was built on old timbers and other organic material that rotted after years of sitting in water. The trail follows a former railroad line.
The collapse also damaged the sewer line that runs under the trail. Experts from the health department and Michigan's Department of Environment, Great Lakes, and Energy found no darkened soil around the pipe, which they said would likely be there if it had been leaking before. The repairs are being done in phases, and the sewer comes first:
- Phase I is complete. It covered material removal, subsurface stabilization, and a temporary sewer pipe repair.
- Phase II is the township's top priority now. It's a permanent sewer line repair that will end the need for bypass pumping in the area. Trustees approved Phases I and II together at $391,500.
- Phase III is paving and trail construction. It brings the estimated total to about $700,000. Trustees plan to put it out for competitive bids.
Much of the work is expected to wrap up this year. Project engineer Prein & Newhof has recommended holding the asphalt paving until spring 2027. The township's August 26 notice says the section will stay closed until then. So this fall's color rides, and likely most of winter, will use the detour along 148th Avenue, State Road, and N. Fruitport Road.
The Detour Uses Pavement That Opened in June
The middle leg of that detour runs on pavement that didn't exist last fall. On June 18, township officials held a ribbon cutting in front of Country Estates for a new 0.5-mile stretch of path on State Road. It connects neighborhoods near 144th Avenue and State Road to the rest of the township's path system and links up with the existing 1-mile path on State Road. The Tribune reported that the extension was finished just in time to become part of the North Bank Trail detour.
The timing works because township voters approved two 10-year millages in November 2024. One renewed 0.47 mills for bike path improvements, and the other added 0.5 mills for new paths. Phase I of the $3.8 million expansion covers the State Road and 152nd Avenue trails. Township Supervisor Jerry Rabideau called the growing system "part of the fabric of our community," and the township now counts more than 25 miles of trails.
Phase II is under construction near the closed stretch of trail. Here's what the township scheduled this summer:
| Path | Side and endpoints | Scheduled start | Expected length of work |
|---|---|---|---|
| Hickory Street | South side, Fruitport Road to 148th Avenue, with crossings at both intersections | Wednesday, July 15 | About eight weeks |
| Rannes Street | North side, linking existing trails on Leonard Road and 152nd Avenue | August 15 | About eight weeks |
Both paths are 8 feet wide, and together they're budgeted at $1,238,909. Crews were scheduled to work weekdays from 7 a.m. to 7 p.m. On that schedule, Hickory should be about done by now and Rannes should be finishing in the next week or so. The township hasn't confirmed either one is finished, so expect some fresh asphalt and maybe some equipment on weekday mornings.
Who Can Ride Where on the Grand Haven Boardwalk
On the city side, the rules changed along with the pavement. Grand Haven City Council unanimously gave final approval to ordinance amendments that ban e-bikes and electric skateboards from the pedestrian boardwalk. The boardwalk is a defined area along the channel that includes Lynne Sherwood Waterfront Stadium and Chinook Pier. Public Safety Director Nichole Hudson said "a lot" of the e-bike complaints her department gets come from the boardwalk.
The new rules are seasonal in one place and year-round in another, and that matters this month:
- Channel boardwalk, year-round: Regular bicycles are allowed. E-bikes and electric skateboards are not, and regular skateboards are still prohibited.
- Washington Avenue sidewalks between Harbor Drive and Third Street: This "no-wheels" zone runs from the last weekend in May through Labor Day. It covers bicycles, skateboards, roller skates, inline skates, and their electric versions. In October, it isn't in effect.
- Mobility devices: Hudson said the ordinance doesn't apply to anyone using a mobility device as defined by the Americans with Disabilities Act.
Councilmember Erin Lyon put it plainly. People are welcome to ride downtown on bikes, scooters, and mopeds, "just not on the sidewalk" in those blocks. Mayor Bob Monetza agreed with other council members that the city needs bike lanes and more bike parking, but noted how little room the city has along its roads.
Dates to Know Through Thanksgiving
With the boardwalk reopening soon and the North Bank Trail closed until spring, here are the fall dates that affect where you can walk:
- Through October 14: Wednesday Grand Haven Farmers Market at 301 Harbor Drive. It stayed put this season because Chinook Pier redevelopment was pushed to 2027. Saturday markets run through October 31.
- Through October 23: Bones About Town puts more than 150 decorated skeletons around town. Fall Fest follows on Saturday, October 24, with Centertown trick-or-treating from 10:30 a.m. to noon.
- Week of October 12: The target date for finishing the Lighthouse Connector Park boardwalk repairs.
- November 20 to 23: North Ottawa Dunes, Ottawa Sands, and P.J. Hoffmaster State Park close to the public for the Lakeshore Wildlife Management firearm hunt. Anyone in the parks without permission will be ticketed, and the parks reopen Tuesday, November 24.
Further out, two Spring Lake projects will add more waterfront walking. Spring Lake Township approved a grant agreement for a pocket park on the Prelwitz Property at Howard Street and Fruitport Road, at the north end of the Petty's Bayou Bridge. A Michigan Natural Resources Trust Fund grant of up to $840,000 would cover 70 percent of the purchase. Early plans call for a fishing and wildlife-viewing deck, a kayak and canoe launch, and a 13-space parking lot, with development likely starting in spring 2028. In the village, North Bank Park, formerly Central Park, received $250,000 from the Grand Haven Area Community Foundation toward a plan with lit paths, a dog park, and a sledding hill. Construction is expected to run from April to July 2027.
That puts the reopened North Bank Trail and the North Bank Park construction in the same 2027 season, with the trail's repaving set for spring and the park's construction scheduled from April to July.
If you're wondering how a closed trail, a new path, or a stretch of construction affects your own street or a home you're considering near the North Bank Trail, Sue can walk you through what's scheduled and when. Contact Capt'n Sue for a private consultation at Suzanne Bladek.